Permit Timeline & Status

Construction Permit Timeline
Applied
July 8, 2026
In Review
1 cycle
Issued
Completed
Expires
1
Days in Applicant Control
1
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Ballard Neighborhood

Project Overview

Project Details
Value
$242,177
Type
Residential Construction
Issued
N/A
Location
Ballard

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Allow housing for one new detached dwelling unit per land use code. Existing garage to be removed and existing detached dwelling unit to remain. Construct new one-family dwelling per plan.

Additional Details

Permit Intelligence
Housing category
Single-Family Add/Alt
Review cycles
1
Days in corrections
1