PERMIT #7151762-BK
601 UNION ST, SEATTLE, WA
newPermit Timeline & Status
Construction Permit Timeline
Applied
July 8, 2026
In Review
1 cycle
Reviews Done
July 15, 2026
Ready to Issue
July 16, 2026
Issued
—
Completed
—
Expires
—
7
Plan Review Days — Total
7
Plan Review Days — City Control
0
Days in Applicant Control
1
Review Cycles
Plan review complete — ready to issue, awaiting final fees/issuance.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$977,000
Type
Commercial Construction
Issued
N/A
Location
Downtown
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Construct blanket permit tenant improvements to JLL on the 28th floor of existing commercial building per plan.
Additional Details
Permit Intelligence
Review cycles
1
Plan review days
7
Days in corrections
0