Addition at 3611 W COMMODORE WAY

3611 W COMMODORE WAY, SEATTLE, WA · Magnolia

Summary

2
Permits
$245,791
Est. value
Aug 25, 2025
First activity
Feb 27, 2026
Latest activity

DeSimone STFI Interior alterations to a single-family residence, subject to field inspection.

Review timeline

Aug 21, 2025 → Feb 27, 2026
Review span
63
Plan review days (total)
44
City control days
19
Applicant correction days
2
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (2)

PermitTypeValueStatusDate
7117045-CN residential $47,600 active Feb 27, 2026
7102767-CN residential $198,191 active Aug 25, 2025

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 80/100 reflects how strongly the permits appear to belong to a single effort.