Addition at 463 CROCKETT ST

463 CROCKETT ST, SEATTLE, WA · Queen Anne

Summary

2
Permits
$155,000
Est. value
Feb 6, 2026
First activity
Jun 8, 2026
Latest activity

Construct repairs to existing retaining wall adjacent to single family residence per plan.

Review timeline

Feb 6, 2026 → Jun 8, 2026
Review span
104
Plan review days (total)
35
City control days
69
Applicant correction days
3
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (2)

PermitTypeValueStatusDate
7123501-CN residential $40,000 active Jun 8, 2026
7128298-CN residential $115,000 new Feb 6, 2026

Participants

No participants on record.

About this project

This project was inferred by grouping related permits at the same address. Confidence score 75/100 reflects how strongly the permits appear to belong to a single effort.