Inferred Project · confidence 75
New construction at 4215 S TRENTON ST
4215 S TRENTON ST, SEATTLE, WA · Rainier ValleySummary
2
Permits
$11,719,385
Est. value
Feb 4, 2026
First activity
Jul 8, 2026
Latest activity
Construct new 2 story Community Center commercial building (mechanical included) occupy per plan.
Review timeline
Dec 30, 2025 → Jul 8, 2026
Review span
190
Plan review days (total)
52
City control days
138
Applicant correction days
6
Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (2)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7110804-CN | commercial | $650,000 | active | Jul 8, 2026 |
| 6967077-CN | commercial | $11,069,385 | pending | Feb 4, 2026 |
Participants
No participants on record.
About this project
This project was inferred by grouping related permits at the same address. Confidence score 75/100 reflects how strongly the permits appear to belong to a single effort.