Inferred Project · confidence 83

Renovation at 151 S ROYAL BROUGHAM WAY

151 S ROYAL BROUGHAM WAY, SEATTLE, WA · SoDo

Summary

8
Permits
$3,125,000
Est. value
Jul 26, 2024
First activity
Jun 22, 2026
Latest activity

KaneBrown & FooFighters at TMobile Park load in on August 15th. Load out on August 19th. Erect temporary stage, cover and scaffold at T-Mobile Park for Kane Brown and Foo Fighters concert 8/16 thru 8/18/2024, per plans. All stage components are provided by stage company and assembled by professional

Review timeline

Jun 26, 2024 → Jun 29, 2026
Review span
48
Plan review days (total)
57
Applicant correction days
5
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (8)

PermitTypeValueStatusDate
7144760-CN commercial $500,000 completed Jun 22, 2026
7148417-CN commercial $500,000 new Jun 16, 2026
7077285-CN commercial $25,000 active Oct 27, 2025
7090699-CN commercial $500,000 active Jul 8, 2025
7077976-CN commercial $500,000 active May 21, 2025
7038869-CN commercial $500,000 completed Sep 20, 2024
7038863-CN industrial $500,000 active Aug 12, 2024
7032584-CN commercial $100,000 active Jul 26, 2024

Participants

No participants on record.

About this project

This project was inferred by grouping related permits at the same address. Confidence score 83/100 reflects how strongly the permits appear to belong to a single effort.