Inferred Project · confidence 75
Tenant improvement at 4540 8TH AVE NE
4540 8TH AVE NE, SEATTLE, WA · WallingfordSummary
2Permits
$10,000Est. value
Jun 4, 2026First activity
Nov 8, 2026Latest activity
Holman Project Construct tenant improvements to existing multifamily building at Units #1701& #1702, per plan.
Review timeline
Apr 28, 2026 → Jun 10, 2026Review span
36Plan review days (total)
33City control days
3Applicant correction days
2Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (2)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7169557-CN | residential | $5,000 | Pending | Nov 8, 2026 |
| 7137165-CN | residential | $5,000 | Completed | Jun 4, 2026 |
Participants
- SERVICEMASTER OF SEATTLE contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 75/100 reflects how strongly the permits appear to belong to a single effort.