Summary
2Permits
$10,800,000Est. value
Sep 30, 2026First activity
Oct 6, 2026Latest activity
Construct site improvements for shoring wall and grading for temporary haul road on adjacent WSDOT property, per plan. (Construct site improvements for temporary haul road on 2 properties, per plan. Review and processing for 2 records under 7161305-CN).
Review timeline
56Applicant correction days
3Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (2)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7161305-CN | commercial | $9,500,000 | New | Oct 6, 2026 |
| 7161306-CN | commercial | $1,300,000 | New | Sep 30, 2026 |
Participants
- M A MORTENSON COMPANY contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 95/100 reflects how strongly the permits appear to belong to a single effort.