Summary
2Permits
$45,000Est. value
Feb 28, 2025First activity
Jul 2, 2026Latest activity
Miller Condo Construct interior alterations to condo units level 12, subject to field inspection, STFI.
Review timeline
Feb 28, 2025 → Jul 2, 2026Review span
0Applicant correction days
0Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (2)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7150945-CN | residential | $25,000 | Active | Jul 2, 2026 |
| 7073065-CN | residential | $20,000 | New | Feb 28, 2025 |
Participants
- MALLET INC contractor