Inferred Project · confidence 78
Tenant improvement at 915 NW 45th ST
915 NW 45th ST, Seattle, WA · FremontSummary
3Permits
$495,000Est. value
Oct 8, 2025First activity
Nov 17, 2026Latest activity
915 NW 45th St - Construction - Tesla Supercharger Expansion Construct site alterations to add stalls to existing vehicle charging station [TESLA] in parking lot of retail commercial building [FRED MEYER-BALLARD], per plan.
Review timeline
Sep 15, 2025 → Dec 16, 2025Review span
22Plan review days (total)
100Applicant correction days
5Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (3)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7171984-CN | commercial | $45,000 | Pending | Nov 17, 2026 |
| 7146954-CN | commercial | $150,000 | New | Jul 13, 2026 |
| 7102768-CN | commercial | $300,000 | Completed | Oct 8, 2025 |
Participants
- WESTERN CONSTRUCTION SRVCS INC contractor
- BLACKSTONE CONSTRUCTION LLC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 78/100 reflects how strongly the permits appear to belong to a single effort.