Inferred Project · confidence 84
Tenant improvement at 1111 3RD AVE
1111 3RD AVE, SEATTLE, WA · DowntownSummary
4Permits
$969,639Est. value
Nov 14, 2024First activity
Nov 3, 2026Latest activity
Forvis Mazars Construct interior, non-structural alterations for private office within existing tenant space #2890 (Forvis Mazars), Subject to Field Inspection (STFI).
Review timeline
Oct 11, 2024 → Nov 3, 2026Review span
165Plan review days (total)
55City control days
110Applicant correction days
5Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (4)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7170312-CN | commercial | $35,000 | Active | Nov 3, 2026 |
| 7102378-CN | commercial | $125,000 | Active | Dec 1, 2025 |
| 7102479-BK | commercial | $750,000 | Active | Nov 19, 2025 |
| 7050509-BK | commercial | $59,639 | Completed | Nov 14, 2024 |
Participants
- GATEWAY CONSTRUCTION SRVCS INC contractor
- DHC CONTRACTING INC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 84/100 reflects how strongly the permits appear to belong to a single effort.