Tenant improvement at 1201 2nd AVE
1201 2nd AVE, Seattle, WA · DowntownSummary
11Permits
$1,560,670Est. value
Aug 16, 2024First activity
Oct 2, 2026Latest activity
Siemens Construct interior non-structural alterations to tenant space at 27th Floor of existing commercial building (Qaltrics Tower at 2+U), subject to field inspection (STFI)
Review timeline
Aug 16, 2024 → Oct 2, 2026Review span
57Plan review days (total)
43City control days
14Applicant correction days
3Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (11)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7165263-CN | commercial | $120,000 | Active | Oct 2, 2026 |
| 7162802-CN | commercial | $70,000 | Active | Sep 16, 2026 |
| 7153138-BK | industrial | $410,815 | Active | Aug 4, 2026 |
| 7144588-CN | commercial | $100,000 | Completed | Jul 30, 2026 |
| 7139908-CN | commercial | $50,000 | Completed | Apr 24, 2026 |
| 7139909-CN | commercial | $50,000 | Completed | Apr 24, 2026 |
| 7112426-CN | commercial | $8,500 | Completed | Nov 18, 2025 |
| 7112165-CN | commercial | $29,500 | Completed | Nov 13, 2025 |
| 7086928-CN | commercial | $61,855 | Active | Oct 31, 2025 |
| 7054317-BK | commercial | $600,000 | Completed | Nov 19, 2024 |
| 7041300-CN | commercial | $60,000 | Completed | Aug 16, 2024 |
Participants
- G L Y CONSTRUCTION INC contractor
- Howard S Wright contractor
- HITT CONTRACTING INC contractor
- JTM CONSTRUCTION INC contractor
- SWINERTON BUILDERS contractor
- OPTIMUS CONST AND DEV INC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 80/100 reflects how strongly the permits appear to belong to a single effort.