Tenant improvement at 1201 WESTERN AVE
1201 WESTERN AVE, SEATTLE, WA · DowntownSummary
7Permits
$1,384,300Est. value
Oct 17, 2024First activity
Oct 19, 2026Latest activity
6th Floor Cushing Terrell Suite Construct blanket permit tenant improvements to Cushing Terrell on the sixth and seventh floors of existing commercial building, per plan.
Review timeline
Sep 9, 2024 → Jul 16, 2026Review span
84Plan review days (total)
36City control days
48Applicant correction days
3Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (7)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7167769-BK | commercial | $555,300 | Pending | Oct 19, 2026 |
| 7122394-CN | commercial | $200,000 | Active | Jul 16, 2026 |
| 7085432-BK | commercial | $299,000 | Active | Aug 20, 2025 |
| 7083623-CN | commercial | $50,000 | Active | Jul 10, 2025 |
| 7085210-BK | commercial | $130,000 | Completed | Jun 3, 2025 |
| 7072105-BK | commercial | $100,000 | Completed | Apr 11, 2025 |
| 7044432-BK | commercial | $50,000 | Completed | Oct 17, 2024 |
Participants
- ABBOTT CONSTRUCTION LLC contractor
- DAVIS SCHUELLER INC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 99/100 reflects how strongly the permits appear to belong to a single effort.