Inferred Project · confidence 95
Tenant improvement at 1551 EASTLAKE AVE E
1551 EASTLAKE AVE E, SEATTLE, WA · South Lake UnionSummary
3Permits
$600,000Est. value
Aug 20, 2026First activity
Nov 10, 2026Latest activity
ARE 1551 Eastlake Tenant Improvement Construct tenant improvements for labs and offices to create separate tenant spaces at floor 1 of existing commercial building, per plan.
Review timeline
Jul 22, 2026 → Nov 10, 2026Review span
53Plan review days (total)
40City control days
13Applicant correction days
5Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (3)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7171472-CN | commercial | $370,000 | Active | Nov 10, 2026 |
| 7155701-CN | commercial | $110,000 | Active | Oct 13, 2026 |
| 7148000-CN | commercial | $120,000 | Active | Aug 20, 2026 |
Participants
- DPR CONSTRUCTION A GEN PRTNRSH contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 95/100 reflects how strongly the permits appear to belong to a single effort.