Inferred Project · confidence 86
Tenant improvement at 1601 2ND AVE
1601 2ND AVE, SEATTLE, WA · DowntownSummary
6Permits
$5,368,257Est. value
Mar 27, 2025First activity
Jul 29, 2026Latest activity
DSA 2nd and Pine Construct blanket permit tenant improvements to the Downtown Seattle Association on the second floor of existing commercial building, per plan.
Review timeline
Jan 28, 2025 → Jul 28, 2026Review span
65Plan review days (total)
44City control days
21Applicant correction days
5Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (6)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7154994-BK | commercial | $2,000,000 | New | Jul 29, 2026 |
| 7145081-BK | commercial | $500,000 | Active | Jul 28, 2026 |
| 7109351-BK | commercial | $1,069,000 | New | Oct 1, 2025 |
| 7089663-BK | commercial | $500,000 | Active | Jul 30, 2025 |
| 7075862-BK | commercial | $1,123,367 | Completed | Jun 10, 2025 |
| 7061985-CN | commercial | $175,890 | Completed | Mar 27, 2025 |
Participants
- SELLEN CONSTR CO INC contractor
- DAVIS SCHUELLER INC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 86/100 reflects how strongly the permits appear to belong to a single effort.