Inferred Project · confidence 87

Tenant improvement at 201 16TH AVE E

201 16TH AVE E, SEATTLE, WA · Capitol Hill

Summary

16Permits
$9,724,820Est. value
Oct 11, 2024First activity
Nov 24, 2026Latest activity

201 16th Ave E - Construction - KP CHM Compressor Replacement Construct alterations to replace compressor equipment at basement level of institutional building [KAISER PERMANENTE CAPITOL HILL], per plan. Mechanical included.

Review timeline

Aug 16, 2024 → Nov 24, 2026Review span
170Plan review days (total)
115City control days
55Applicant correction days
12Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (16)

PermitTypeValueStatusDate
7147767-CN commercial $657,100 Active Nov 24, 2026
7168935-CN commercial $25,000 Active Nov 17, 2026
7147938-CN commercial $506,800 Active Nov 4, 2026
7147950-CN commercial $441,437 New Oct 7, 2026
7132347-CN commercial $2,120,000 Active Sep 10, 2026
7147546-CN commercial $461,000 Completed Aug 21, 2026
7142117-CN commercial $356,200 Completed Aug 5, 2026
7127049-CN commercial $65,000 Completed Apr 8, 2026
7090667-CN commercial $2,937,342 Active Nov 17, 2025
7094220-CN commercial $396,689 Active Sep 10, 2025
7089875-CN commercial $93,009 Active Aug 12, 2025
7051841-CN commercial $75,007 Completed Feb 20, 2025
7041824-CN commercial $241,457 Completed Jan 17, 2025
7052967-CN commercial $460,840 Completed Jan 8, 2025
7045325-CN commercial $270,000 Completed Oct 21, 2024
7033251-CN commercial $617,939 Completed Oct 11, 2024

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 87/100 reflects how strongly the permits appear to belong to a single effort.