Inferred Project · confidence 83
Tenant improvement at 2122 7TH AVE
2122 7TH AVE, SEATTLE, WA · DowntownSummary
5
Permits
$1,566,000
Est. value
Jul 8, 2025
First activity
Mar 12, 2026
Latest activity
The Summit (SEA47) 2nd Floor Tenant Improvement Tenant improvement to expand an existing server rack room from 12 SF to 66.64 SF. Scope of work to include demolition and new non-structural partition wall. No change of use/ occupancy with this application. (subject to field inspection, STFI)
Review timeline
Jun 26, 2025 → Mar 12, 2026
Review span
19
Plan review days (total)
10
City control days
9
Applicant correction days
2
Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (5)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7132848-CN | commercial | $20,000 | active | Mar 12, 2026 |
| 7113798-BK | commercial | $1,500,000 | active | Jan 20, 2026 |
| 7095676-CN | commercial | $3,000 | active | Jul 14, 2025 |
| 7094909-CN | commercial | $3,000 | active | Jul 10, 2025 |
| 7093339-CN | commercial | $40,000 | completed | Jul 8, 2025 |
Participants
- G L Y CONSTRUCTION INC contractor
- CORTI CONSTRUCTION INC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 83/100 reflects how strongly the permits appear to belong to a single effort.