Inferred Project · confidence 87

Tenant improvement at 305 HARRISON ST

305 HARRISON ST, SEATTLE, WA · Belltown

Summary

5
Permits
$4,005,000
Est. value
Aug 20, 2024
First activity
Sep 18, 2024
Latest activity

Bumbershoot 2024 Install Skateboard Half Pipe Ramp, per plan [Temporary Structure Permit to erect 2 (two) temporary stages with speaker delay towners, skateboarding ramp and Geodesic Domes at Fisher Plaza for Bumbershoot 2024 at Seattle Center on August 31st and occupy until September 2nd; review an

Permit records (5)

PermitTypeValueStatusDate
7024106-CN commercial $5,000 completed Sep 18, 2024
7040560-CN commercial $1,000,000 new Aug 23, 2024
7040765-CN commercial $1,000,000 completed Aug 23, 2024
7040764-CN commercial $1,000,000 completed Aug 20, 2024
7040766-CN commercial $1,000,000 completed Aug 20, 2024

Participants

No participants on record.

About this project

This project was inferred by grouping related permits at the same address. Confidence score 87/100 reflects how strongly the permits appear to belong to a single effort.