Inferred Project · confidence 86

Tenant improvement at 500 5TH AVE N

500 5TH AVE N, SEATTLE, WA · South Lake Union

Summary

6
Permits
$992,360
Est. value
May 31, 2024
First activity
Jan 22, 2026
Latest activity

BMGF-S2 Doors Construct interior alterations to level S2 office space of Bill and Melinda Gates Foundation South Building, per plot plan and Subject to Field Inspection (STFI)

Review timeline

May 29, 2024 → Apr 9, 2026
Review span
13
Plan review days (total)
13
City control days
0
Applicant correction days
1
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (6)

PermitTypeValueStatusDate
7121537-CN commercial $500 completed Jan 22, 2026
7107514-CN commercial $200,000 completed Sep 19, 2025
7093947-CN commercial $15,000 completed Jul 6, 2025
7080131-CN commercial $323,860 completed Jun 6, 2025
7070605-CN commercial $450,000 completed Feb 18, 2025
7027698-CN commercial $3,000 completed May 31, 2024

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 86/100 reflects how strongly the permits appear to belong to a single effort.