Inferred Project · confidence 92
Tenant improvement at 509 OLIVE WAY
509 OLIVE WAY, SEATTLE, WA · DowntownSummary
10Permits
$3,028,528Est. value
May 5, 2025First activity
Nov 14, 2026Latest activity
509 Olive Way Landlord Project Construct alterations to exterior storefront at ground level, doors and access ramp of Suite A, at landmark Medical Dental Building, per plan.
Review timeline
Jan 28, 2025 → Nov 14, 2026Review span
228Plan review days (total)
127City control days
101Applicant correction days
11Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (10)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7163803-BK | commercial | $275,000 | Active | Nov 14, 2026 |
| 7163807-BK | commercial | $250,000 | Active | Nov 14, 2026 |
| 7163805-BK | commercial | $400,000 | Active | Nov 14, 2026 |
| 7163798-BK | commercial | $258,000 | Active | Nov 13, 2026 |
| 7163796-BK | commercial | $350,000 | Active | Oct 19, 2026 |
| 7156258-BK | commercial | $750,000 | New | Aug 13, 2026 |
| 7105361-BK | commercial | $473,957 | Completed | Oct 23, 2025 |
| 7085161-CN | commercial | $40,219 | Completed | Aug 19, 2025 |
| 7079762-CN | commercial | $201,352 | Completed | May 28, 2025 |
| 7052625-CN | commercial | $30,000 | Active | May 5, 2025 |
Participants
- MASTEC NETWORK SOLUTIONS INC contractor
- WALEN CONSTRUCTION LLC contractor
- CHAIN CONSTRUCTION LLC contractor
- Chain Construction contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 92/100 reflects how strongly the permits appear to belong to a single effort.