Tenant improvement at 700 DEXTER AVE N

700 DEXTER AVE N, SEATTLE, WA · South Lake Union

Summary

7Permits
$1,430,000Est. value
Aug 6, 2025First activity
Nov 18, 2026Latest activity

Construction Permit TI bathrooms Construct tenant improvements office at restrooms on levels 8, 9, 10, 11, 12, 14 ,15 of existing commercial building, per plan.

Review timeline

Jul 9, 2025 → Nov 16, 2026Review span
230Plan review days (total)
216City control days
14Applicant correction days
9Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (7)

PermitTypeValueStatusDate
7159202-CN commercial $50,000 Pending Nov 18, 2026
7168873-CN commercial $250,000 Active Nov 16, 2026
7139309-CN commercial $100,000 New Sep 14, 2026
7124329-CN commercial $150,000 Active Jul 27, 2026
7144364-CN commercial $30,000 Completed Jul 7, 2026
7093553-CN commercial $500,000 Completed Oct 17, 2025
7094450-CN commercial $350,000 Completed Aug 6, 2025

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 81/100 reflects how strongly the permits appear to belong to a single effort.