Inferred Project · confidence 80
Tenant improvement at 837 N 34TH ST
837 N 34TH ST, SEATTLE, WA · Queen AnneSummary
2
Permits
$4,354,100
Est. value
May 30, 2025
First activity
Apr 13, 2026
Latest activity
Kiln Seattle (Freemont): TI Construct tenant improvements in commercial building on fourth floor, occupy per plan. Mechanical is included.
Review timeline
Apr 2, 2025 → Apr 13, 2026
Review span
69
Plan review days (total)
62
City control days
7
Applicant correction days
2
Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (2)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7122911-CN | commercial | $2,981,600 | active | Apr 13, 2026 |
| 7076797-CN | commercial | $1,372,500 | completed | May 30, 2025 |
Participants
- FOUSHEE & ASSOCIATES CO INC contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 80/100 reflects how strongly the permits appear to belong to a single effort.