Inferred Project · confidence 100

Tenant improvement at 901 3RD AVE

901 3RD AVE, SEATTLE, WA · Downtown

Summary

2
Permits
$300,000
Est. value
Aug 8, 2025
First activity
Mar 3, 2026
Latest activity

999 3RD - SUITE 600 - FENNEMORE Construct blanket permit tenant improvements to Fennemore on the sixth floor of existing commercial building, per plan.

Review timeline

Jul 21, 2025 → May 15, 2026
Review span
7
Plan review days (total)
7
City control days
0
Applicant correction days
1
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (2)

PermitTypeValueStatusDate
7130532-BK commercial $200,000 completed Mar 3, 2026
7097046-BK commercial $100,000 completed Aug 8, 2025

Participants

About this project

This project was inferred by grouping related permits at the same address. Confidence score 100/100 reflects how strongly the permits appear to belong to a single effort.