PERMIT #7009759-CN
527 31ST AVE E, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
October 28, 2024
In Review
—
Issued
April 9, 2025
Completed
January 7, 2026
Expires
October 9, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$150,000
Type
Residential Construction
Issued
April 9, 2025
Location
Madrona
Contractor Information
Location & Map
Project Description
529 31st AVE E - New DADU Allow new detached accessory dwelling unit per green building standard requirements to existing single-family use, per land use code. Construct new one family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BUCKTTC832BT
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0045176
Expires
October 9, 2026
Existing units
1
Sleeping rooms
2