PERMIT #7020606-CN

2810 E MARION ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
September 24, 2025
In Review
3 cycles
Reviews Done
April 15, 2026
Ready to Issue
April 22, 2026
Issued
April 22, 2026
Completed
Expires
October 22, 2027
203
Plan Review Days — Total
63
Plan Review Days — City Control
140
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$373,738
Type
Residential Construction
Issued
April 22, 2026
Location
Central District

Contractor Information

Contractor
BIG BEN'S CONSTRUCTION LLC
General Contractor
License BIGBEBC823C2

Location & Map

Project Description
Construction Permit: new sfr/aadu Establish use as single-family residence with attached accessory dwelling unit per land use code. Construct two-family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BIGBEBC823C2
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0083652
Related land-use permit
3041816-LU
Review cycles
3
Plan review days
203
Days in corrections
140
Expires
October 22, 2027
Existing units
0
Units added
2
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor