PERMIT #7021243-CN
2001 W GARFIELD ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
August 27, 2025
In Review
4 cycles
Issued
March 18, 2026
Completed
—
Expires
September 18, 2027
203
Plan Review Days — Total
104
Plan Review Days — City Control
99
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2001 W GARFIELD ST, SEATTLE, WA Property
Demolition at 2001 W GARFIELD ST Project
Other Seattle Neighborhood
Project Overview
Project Details
Value
$120,545
Type
Industrial Construction
Issued
March 18, 2026
Location
Other Seattle
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Terminal 91 Berths 6 & 8 Redevelopment Install south Modular Building A, occupy per plan. (Construct site improvements and foundation work to install (2) modular buildings at pier 90, per plan. Review & process for (2) records under 7021243-CN)
Additional Details
Permit Intelligence
Work performed by
Authorized Government Representative
Review level
Full C
Primary use
Industrial
Parcel
DV0082010
Review cycles
4
Plan review days
203
Days in corrections
99
Expires
September 18, 2027