PERMIT #7038406-CN
800 OCCIDENTAL AVE S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
August 5, 2024
In Review
—
Issued
August 29, 2024
Completed
September 5, 2024
Expires
September 1, 2024
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Other Seattle Neighborhood
Project Overview
Project Details
Value
$500,000
Type
Commercial Construction
Issued
August 29, 2024
Location
Other Seattle
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Metallica at Lumen Field Erect temporary stage, cover and scaffold at Lumen Field for Metallica Concert on Saturday August 31st, per plans. All stage components are provided by stage company and assembled by professional crew. Owner responsible for integrity of structure.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Commercial
Parcel
DV0066517
Expires
September 1, 2024
Existing units
0
Sleeping rooms
0