PERMIT #7046515-CN
10043 8TH AVE NW, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
November 14, 2024
In Review
—
Issued
March 24, 2025
Completed
February 10, 2026
Expires
September 24, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
10043 8TH AVE NW, SEATTLE, WA Property
Demolition at 10043 8TH AVE NW Project
OLSEN ANDERSON CONST LLC Contractor
Greenwood Neighborhood
Project Overview
Project Details
Value
$836,225
Type
Residential Construction
Issued
March 24, 2025
Location
Greenwood
Contractor Information
Location & Map
Project Description
OA 8TH AVENUE HOMES Construct east two-family dwelling (Establish use as single-family residence with attached and detached accessory dwelling unit per land use code. Construct (1) two-family dwelling & (1) one-family dwelling, per plan. Review & process for (2) records under 7046515-CN)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
OLSENAC813OC
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1136326
Expires
September 24, 2026
Existing units
0
Sleeping rooms
0