PERMIT #7047370-CN
2501 15TH AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
December 23, 2025
In Review
3 cycles
Reviews Done
April 1, 2026
Ready to Issue
April 1, 2026
Issued
April 1, 2026
Completed
—
Expires
October 1, 2027
99
Plan Review Days — Total
38
Plan Review Days — City Control
61
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2501 15TH AVE W, SEATTLE, WA Property
Renovation at 2501 15TH AVE W Project
MASTEC NETWORK SOLUTIONS INC Contractor
Interbay Neighborhood
Project Overview
Project Details
Value
$30,000
Type
Commercial Construction
Issued
April 1, 2026
Location
Interbay
Contractor Information
Location & Map
Project Description
Construction Permit Construct alterations to telecommunications facility (AT&T), per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MASTENS876KN
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0020778
Review cycles
3
Plan review days
99
Days in corrections
61
Expires
October 1, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0