PERMIT #7048365-CN

800 Occidental AVE S, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
November 9, 2024
In Review
Issued
March 10, 2025
Completed
March 10, 2025
Expires
September 10, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$150,000
Type
Commercial Construction
Issued
March 10, 2025
Location
Other Seattle

Contractor Information

Contractor
G L Y CONSTRUCTION INC
General Contractor
License GLYCOI*018O9

Location & Map

Project Description
Construction Permit Tenant improvements at stadium (Lumen field) at Suites 8 & 9, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GLYCOI*018O9
Review level
Full +
Primary use
Commercial
Parcel
DV0066517
Expires
September 10, 2026
Existing units
0
Sleeping rooms
0
Open official SDCI detail →