PERMIT #7050092-DM
9741 8TH AVE NW, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
January 15, 2026
In Review
0 cycles
Ready to Issue
July 7, 2026
Issued
July 7, 2026
Completed
—
Expires
—
0
Days in Applicant Control
0
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$1,000,000
Type
Residential Construction
Issued
July 7, 2026
Location
Greenwood
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Demolish one-family dwelling and associated accessory structures subject to field inspection [STFI].
Additional Details
Permit Intelligence
Review level
Field
Primary use
Single Family/Duplex
Parcel
DV1186762
Review cycles
0
Days in corrections
0
Units added
3
Units removed
1