PERMIT #7050292-CN
800 OCCIDENTAL AVE S, SEATTLE, WA
completedPermit Timeline & Status
Construction Permit Timeline
Applied
December 13, 2024
In Review
—
Issued
March 10, 2025
Completed
August 4, 2025
Expires
September 10, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
800 OCCIDENTAL AVE S, SEATTLE, WA Property
M A MORTENSON COMPANY Contractor
Other Seattle Neighborhood
Project Overview
Project Details
Value
$125,000
Type
Commercial Construction
Issued
March 10, 2025
Location
Other Seattle
Contractor Information
Location & Map
Project Description
Lumen North Lot Improvements Construct alterations to north parking lot of existing stadium (Lumen Field), per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MAMORC*190N6
Review level
Full +
Primary use
Commercial
Parcel
DV0066517
Expires
September 10, 2026
Existing units
0
Sleeping rooms
0