Permit Timeline & Status

Construction Permit Timeline
Applied
December 13, 2024
In Review
Issued
March 10, 2025
Completed
August 4, 2025
Expires
September 10, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$125,000
Type
Commercial Construction
Issued
March 10, 2025
Location
Other Seattle

Contractor Information

Contractor
M A MORTENSON COMPANY
General Contractor
License MAMORC*190N6

Location & Map

Project Description
Lumen North Lot Improvements Construct alterations to north parking lot of existing stadium (Lumen Field), per plan

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MAMORC*190N6
Review level
Full +
Primary use
Commercial
Parcel
DV0066517
Expires
September 10, 2026
Existing units
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor