PERMIT #7059594-CN

800 OCCIDENTAL AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
December 9, 2024
In Review
Issued
January 22, 2025
Completed
Expires
February 5, 2025
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$9,000
Type
Commercial Construction
Issued
January 22, 2025
Location
Other Seattle

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Seattle Boat Show Duck Temporary installation of Rubber Duck sculpture at level 6 of Lumen Field Parking Garage, per plan. Installation will be in place for two weeks, starting on 1/27/2025.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full
Primary use
Commercial
Parcel
DV0066517
Expires
February 5, 2025
Existing units
0
Sleeping rooms
0
Open official SDCI detail →
Open Map