PERMIT #7070520-CN

2562 13TH AVE W, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
August 22, 2025
In Review
3 cycles
Issued
April 12, 2026
Completed
Expires
October 12, 2027
231
Plan Review Days — Total
47
Plan Review Days — City Control
184
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Interbay Neighborhood

Project Overview

Project Details
Value
$759,761
Type
Residential Construction
Issued
April 12, 2026
Location
Interbay

Contractor Information

Contractor
Owner/Lessee

Location & Map

Project Description
Queen Anne New House Establish use as single family residence per land use code. Construct new one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1223337
Review cycles
3
Plan review days
231
Days in corrections
184
Expires
October 12, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
Open Map