PERMIT #7073533-CN

117 32ND AVE S, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
September 30, 2025
In Review
3 cycles
Reviews Done
June 16, 2026
Ready to Issue
June 17, 2026
Issued
June 17, 2026
Completed
Expires
259
Plan Review Days — Total
103
Plan Review Days — City Control
156
Days in Applicant Control
3
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Central District Neighborhood

Project Overview

Project Details
Value
$224,885
Type
Residential Construction
Issued
June 17, 2026
Location
Central District

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Establish use for the record for a 5-unit apartment to 1971 and construct alterations to existing basement unit of an existing five-unit multifamily building occupy per plan.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Multifamily
Parcel
DV0028483
Review cycles
3
Plan review days
259
Days in corrections
156
Units added
1
Units removed
0
Open Map