Construction Permit Timeline
Applied
April 16, 2025
In Review
—
Issued
June 10, 2025
Completed
June 10, 2025
Expires
December 10, 2026
All reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
800 OCCIDENTAL AVE S, SEATTLE, WA Property
Other Seattle Neighborhood
Project Overview
Project Details
Value
$25
Type
Commercial Construction
Issued
June 10, 2025
Location
Other Seattle
Contractor Information
Contractor
Not published by SDCI
Location & Map
Project Description
Building Permit - FCWC25 Install temporary improvements in zone 3 - NE entrance tent and fenced enclosure w/ gates, per plan (Install temporary improvements in zones 1, 2, 3, 4 & within Lumen Field from June 12th – June 25th. Review & process for (5) records under 7075306-CN)
Additional Details
Permit Intelligence
Work performed by
Other Exemption from RCW 18.27.090
Review level
Dependent Building
Primary use
Commercial
Parcel
DV0066517
Expires
December 10, 2026