Permit Timeline & Status

Construction Permit Timeline
Applied
April 16, 2025
In Review
Issued
June 10, 2025
Completed
June 10, 2025
Expires
December 10, 2026
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$25
Type
Commercial Construction
Issued
June 10, 2025
Location
Other Seattle

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Building Permit - FCWC25 Install temporary improvements in zone 3 - NE entrance tent and fenced enclosure w/ gates, per plan (Install temporary improvements in zones 1, 2, 3, 4 & within Lumen Field from June 12th – June 25th. Review & process for (5) records under 7075306-CN)

Additional Details

Permit Intelligence
Work performed by
Other Exemption from RCW 18.27.090
Review level
Dependent Building
Primary use
Commercial
Parcel
DV0066517
Expires
December 10, 2026