PERMIT #7079581-CN

335 THOMAS ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
August 21, 2025
In Review
4 cycles
Issued
December 16, 2025
Completed
Expires
June 16, 2027
116
Plan Review Days — Total
43
Plan Review Days — City Control
73
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$70,000
Type
Commercial Construction
Issued
December 16, 2025
Location
Belltown

Contractor Information

Contractor
STERLING Telecom & Const Inc
General Contractor
License STERLTC884C9

Location & Map

Project Description
Verizon Wireless EXPO DAS Node 2 Construct new light pole with telecommunication antennae south of the Armory, per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
STERLTC884C9
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0358080
Review cycles
4
Plan review days
116
Days in corrections
73
Expires
June 16, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor