Inferred Project · confidence 80
New construction at 335 THOMAS ST
335 THOMAS ST, SEATTLE, WA · BelltownSummary
5Permits
$270,000Est. value
Apr 17, 2025First activity
Sep 16, 2026Latest activity
335 Thomas St - Construction - Verizon EXPO DAS Node 3 Replace existing light pole with new light pole to include integrated small wireless antennas and equipment for minor telecommunications facility [VERIZON] on institutional campus [SEATTLE CENTER], per plan.
Review timeline
Mar 6, 2025 → Nov 10, 2026Review span
252Plan review days (total)
103City control days
149Applicant correction days
12Review cycles
Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.
Permit records (5)
| Permit | Type | Value | Status | Date |
|---|---|---|---|---|
| 7148933-CN | commercial | $70,000 | Completed | Sep 16, 2026 |
| 7126917-CN | commercial | $50,000 | Completed | Mar 31, 2026 |
| 7079760-CN | commercial | $70,000 | Completed | Dec 20, 2025 |
| 7079581-CN | commercial | $70,000 | Active | Dec 16, 2025 |
| 7073935-CN | commercial | $10,000 | Completed | Apr 17, 2025 |
Participants
- STERLING Telecom & Const Inc contractor
About this project
This project was inferred by grouping related permits at the same address. Confidence score 80/100 reflects how strongly the permits appear to belong to a single effort.