4
Permits
$200,000
Est. value
Apr 17, 2025
First activity
Mar 31, 2026
Latest activity

335 Thomas St - Construction - Verizon EXPO DAS Node 3 Replace existing light pole with new light pole to include integrated small wireless antennas and equipment for minor telecommunications facility [VERIZON] on institutional campus [SEATTLE CENTER], per plan.

Review timeline

Mar 6, 2025 → Jun 18, 2026
Review span
229
Plan review days (total)
93
City control days
136
Applicant correction days
10
Review cycles

Plan-review metrics aggregated across this project's permits, from Seattle DCI. "City control days" is total plan-review days minus the days applicants held permits for corrections.

Permit records (4)

PermitTypeValueStatusDate
7126917-CN commercial $50,000 completed Mar 31, 2026
7079760-CN commercial $70,000 completed Dec 20, 2025
7079581-CN commercial $70,000 active Dec 16, 2025
7073935-CN commercial $10,000 completed Apr 17, 2025

Participants