Permit Timeline & Status

Construction Permit Timeline
Applied
October 22, 2025
In Review
4 cycles
Reviews Done
December 19, 2025
Ready to Issue
December 19, 2025
Issued
December 20, 2025
Completed
June 18, 2026
Expires
June 20, 2027
58
Plan Review Days — Total
31
Plan Review Days — City Control
27
Days in Applicant Control
4
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.

Project Overview

Project Details
Value
$70,000
Type
Commercial Construction
Issued
December 20, 2025
Location
Belltown

Contractor Information

Contractor
STERLING Telecom & Const Inc
General Contractor
License STERLTC884C9

Location & Map

Project Description
335 Thomas St - Construction - Verizon EXPO DAS Node 3 Replace existing light pole with new light pole to include integrated small wireless antennas and equipment for minor telecommunications facility [VERIZON] on institutional campus [SEATTLE CENTER], per plan.

Additional Details

Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
STERLTC884C9
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0358080
Review cycles
4
Plan review days
58
Days in corrections
27
Expires
June 20, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →