PERMIT #7083689-CN
419 OCCIDENTAL AVE S, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 12, 2025
In Review
2 cycles
Reviews Done
November 5, 2025
Ready to Issue
November 6, 2025
Issued
March 5, 2026
Completed
—
Expires
September 5, 2027
54
Plan Review Days — Total
33
Plan Review Days — City Control
21
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$654,163
Type
Commercial Construction
Issued
March 5, 2026
Location
Pioneer Square
Contractor Information
Location & Map
Project Description
419 Occidental L2 Establish a mixed use of arts facility, offices and general retail sales and services, per land use code. Construct tenant improvements for multi-use arts facility at level 2 of existing commercial building, occupy per plan
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
MALLEI*012DB
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0013204
Review cycles
2
Plan review days
54
Days in corrections
21
Expires
September 5, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0