PERMIT #7089561-CN
823 20TH AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
August 19, 2025
In Review
2 cycles
Issued
October 1, 2025
Completed
—
Expires
April 1, 2027
43
Plan Review Days — Total
28
Plan Review Days — City Control
15
Days in Applicant Control
2
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
823 20TH AVE, SEATTLE, WA Property
Renovation at 823 20TH AVE Project
AMAYA BUILDER LLC Contractor
Central District Neighborhood
Project Overview
Project Details
Value
$251,193
Type
Residential Construction
Issued
October 1, 2025
Location
Central District
Contractor Information
Location & Map
Project Description
823 20th Ave - Construction - Stallman Remodel Construct substantial alterations and additions for single-family residence, per plan.
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
AMAYABL779ON
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0022437
Review cycles
2
Plan review days
43
Days in corrections
15
Expires
April 1, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0