PERMIT #7091987-CN
9553 EVANSTON AVE N, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 2, 2025
In Review
3 cycles
Issued
December 16, 2025
Completed
—
Expires
June 16, 2027
105
Plan Review Days — Total
90
Plan Review Days — City Control
15
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
9553 EVANSTON AVE N, SEATTLE, WA Property
Addition at 9553 EVANSTON AVE N Project
REVISION HOMES INC Contractor
Greenwood Neighborhood
Project Overview
Project Details
Value
$141,800
Type
Residential Construction
Issued
December 16, 2025
Location
Greenwood
Contractor Information
Location & Map
Project Description
9553 Evanston Ave N - Construction Permit Construct substantial alterations and porch addition to EAST one-family dwelling, per plan. [Allow accessory dwelling units to existing single-family use, per Land Use Code. Construct 2 one-family dwellings and substantial alterations and porch addition to existing one-family dwelling, per plan. Review and processing for (3) construction records under 7091987-CN.]
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
REVISHI851PO
Housing category
Single-Family Add/Alt
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1171682
Review cycles
3
Plan review days
105
Days in corrections
15
Expires
June 16, 2027
Existing units
1
Units added
0
Units removed
0
Sleeping rooms
0