PERMIT #7093364-CN
721 N 92ND ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 8, 2025
In Review
3 cycles
Reviews Done
March 16, 2026
Ready to Issue
March 20, 2026
Issued
March 20, 2026
Completed
—
Expires
September 20, 2027
189
Plan Review Days — Total
123
Plan Review Days — City Control
66
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$357,031
Type
Residential Construction
Issued
March 20, 2026
Location
Greenwood
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
Construction Permit Construct west one family dwelling, per plan. (Establish use as single family residences and duplex per land use code. Construct new one and two family dwellings, per plan. Review and processing for three records under 7093364-CN)
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV1158345
Review cycles
3
Plan review days
189
Days in corrections
66
Expires
September 20, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
0