PERMIT #7095077-CN
2516 10TH AVE W, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
October 1, 2025
In Review
4 cycles
Reviews Done
February 2, 2026
Ready to Issue
February 3, 2026
Issued
February 3, 2026
Completed
—
Expires
August 3, 2027
124
Plan Review Days — Total
113
Plan Review Days — City Control
11
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$250,000
Type
Residential Construction
Issued
February 3, 2026
Location
Interbay
Contractor Information
Location & Map
Project Description
Daren Doss Construct additions and alterations to existing (west) one-family dwelling, per plan. (Allow new detached accessory dwelling unit to existing single family use per land use code. Construct addition to existing one family dwelling and construct new one family dwelling, per plan. Review and processing for two records under 7095077-CN.)
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
BUCKTTC832BT
Housing category
Single-Family Add/Alt
Review level
Full C
Primary use
Single Family/Duplex
Parcel
DV0013087
Review cycles
4
Plan review days
124
Days in corrections
11
Expires
August 3, 2027
Existing units
0
Units added
1
Units removed
0
Sleeping rooms
1