PERMIT #7098134-DM

218 31ST AVE E, SEATTLE, WA

completed

Permit Timeline & Status

Construction Permit Timeline
Applied
October 27, 2025
In Review
2 cycles
Reviews Done
March 3, 2026
Ready to Issue
May 29, 2026
Issued
May 29, 2026
Completed
July 23, 2026
Expires
127
Plan Review Days — Total
31
Plan Review Days — City Control
96
Days in Applicant Control
2
Review Cycles
Next stepAll reviews complete — permit closed out.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Madrona Neighborhood

Project Overview

Project Details
Value
$1,361,221
Type
Residential Construction
Issued
May 29, 2026
Location
Madrona

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Demolish existing two family dwelling per plan.

Additional Details

Permit Intelligence
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1216753
Review cycles
2
Plan review days
127
Days in corrections
96
Units added
0
Units removed
2