PERMIT #7098758-CN
1816 26TH AVE, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 9, 2025
In Review
3 cycles
Reviews Done
February 10, 2026
Ready to Issue
February 10, 2026
Issued
February 10, 2026
Completed
—
Expires
August 10, 2027
154
Plan Review Days — Total
82
Plan Review Days — City Control
72
Days in Applicant Control
3
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Project Overview
Project Details
Value
$72,000
Type
Residential Construction
Issued
February 10, 2026
Location
Central District
Contractor Information
Location & Map
Project Description
Tolliver Foundation Repair Install helical piles to stabilize portions of foundation of a single-family residence, per plans
Additional Details
Permit Intelligence
Work performed by
Licensed Contractor
Contractor license
GROUN**763O5
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1173844
Review cycles
3
Plan review days
154
Days in corrections
72
Expires
August 10, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0