PERMIT #7101228-CN

404 N 105TH ST, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
October 21, 2025
In Review
5 cycles
Reviews Done
June 15, 2026
Ready to Issue
June 16, 2026
Issued
June 18, 2026
Completed
Expires
237
Plan Review Days — Total
40
Plan Review Days — City Control
197
Days in Applicant Control
5
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Greenwood Neighborhood

Project Overview

Project Details
Value
$25,000
Type
Commercial Construction
Issued
June 18, 2026
Location
Greenwood

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct alterations to existing monopole per plan.

Additional Details

Permit Intelligence
Housing category
Commercial Add/Alt
Review level
Full +
Primary use
Commercial
Parcel
DV0057696
Review cycles
5
Plan review days
237
Days in corrections
197
Units added
0
Units removed
0
Open Map