PERMIT #7101933-CN
2011 E TERRACE ST, SEATTLE, WA
activePermit Timeline & Status
Construction Permit Timeline
Applied
September 4, 2025
In Review
4 cycles
Issued
January 13, 2026
Completed
—
Expires
July 13, 2027
130
Plan Review Days — Total
55
Plan Review Days — City Control
75
Days in Applicant Control
4
Review Cycles
Permit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
2011 E TERRACE ST, SEATTLE, WA Property
Central District Neighborhood
Project Overview
Project Details
Value
$400,000
Type
Residential Construction
Issued
January 13, 2026
Location
Central District
Contractor Information
Contractor
Owner/Lessee
Location & Map
Project Description
2011 E Terrace St - Construction add AADU Establish use as single-family residence and attached accessory dwelling unit per land use code. Construct substantial alterations and additions and convert one-family dwelling to two-family dwelling, per plan.
Additional Details
Permit Intelligence
Work performed by
Owner/Lessee
Housing category
Single-Family Add/Alt
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV1109332
Review cycles
4
Plan review days
130
Days in corrections
75
Expires
July 13, 2027
Existing units
1
Units added
1
Units removed
0
Sleeping rooms
0