PERMIT #7104150-CN

1715 30TH AVE, SEATTLE, WA

pending

Permit Timeline & Status

Construction Permit Timeline
Applied
June 18, 2026
In Review
0 cycles
Issued
Completed
Expires
0
Days in Applicant Control
0
Review Cycles
Next stepIn City review — awaiting the next action.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Central District Neighborhood

Project Overview

Project Details
Value
$1,009,245
Type
Residential Construction
Issued
N/A
Location
Central District

Contractor Information

Contractor
Not published by SDCI

Location & Map

Project Description
Construct new east townhouse building per plan (Establish use as housing for 5 attached dwelling units in two structures per land use code. Construct new townhouse building and new two family dwelling per plan. Review and processing for 2 records under 7104150-CN)

Additional Details

Permit Intelligence
Related land-use permit
3043293-LU
Review cycles
0
Days in corrections
0
Open Map