PERMIT #7104601-CN

215 31ST AVE, SEATTLE, WA

active

Permit Timeline & Status

Construction Permit Timeline
Applied
November 5, 2025
In Review
4 cycles
Reviews Done
March 25, 2026
Ready to Issue
March 26, 2026
Issued
March 26, 2026
Completed
Expires
September 26, 2027
140
Plan Review Days — Total
64
Plan Review Days — City Control
76
Days in Applicant Control
4
Review Cycles
Next stepPermit issued — construction underway.
Plan-review data from Seattle DCI. “City control” is total plan-review days minus the days the applicant held the permit for corrections.
Explore This Record
Central District Neighborhood

Project Overview

Project Details
Value
$752,098
Type
Residential Construction
Issued
March 26, 2026
Location
Central District

Contractor Information

Contractor
LUCID HOME DESIGNS
General Contractor
License LUCIDHD791NR

Location & Map

Project Description
New SFR Construction of new one family dwelling, per plan.

Additional Details

Permit Intelligence
Work performed by
Owner/Lessee
Contractor license
LUCIDHD791NR
Review level
Full +
Primary use
Single Family/Duplex
Parcel
DV0362541
Related land-use permit
3043302-LU
Review cycles
4
Plan review days
140
Days in corrections
76
Expires
September 26, 2027
Existing units
0
Units added
0
Units removed
0
Sleeping rooms
0
Open official SDCI detail →
View Contractor